Appellate Terms of the Supreme Court of New York June 15, 1908 (Alexander v. Costello)

Also known as

United States · · · 15-06-1908

Per Curiam.

The action was brought to foreclose a mechanic’s lien. The notice of lien recites that the “ agreed

*492price or value ” of the labor performed and materials furnished is $1,175. The validity of the lien cannot be upheld, since this statement in the disjunctive is not in compliance with the law. Siegel v. Ehrshowsky, 46 Misc. Rep. 605.