Supreme Court of Virginia June 12, 1913 (United States v. Wm. R. Trigg Co.)
Also known as
United States · · · 12-06-1913
lead-opinion
Harrison, J.,
delivered the opinion of the court.
This case has several times been before this court, the last time under the style of Hawes & Co. v. Wm. R. Trigg Co., 110 Va. 165, 65 S. E. 538, which was on appeal reviewed by the Supreme Court of the United States under the style of “United States v. Ansonia Brass & Copper Co., 218 U. S. 452, 54 L. Ed. 1107, 31 Sup. Ct. 49.
At the time these insolvency proceedings were instituted against the appellee company, there were three vessels, for the United States, in process of construction at its shipyard at Richmond, Va., namely, a sea-going suction dredge for the War Department, called the “Benyuard,” a revenue cutter for the Treasury Department, called the “Mohawk,” and a cruiser for the Navy Department, called the “Galveston.” In the progress of this litigation it has been finally decided by the Supreme Court that the “Benyuard” belonged to the United States, and that it was not liable for the debts of the appellee. All controversy as to this vessel is, therefore at an end, and it is no longer involved in this suit.
It has also been finally settled by this court in Hawes & Co. v. Trigg Co., supra, and affirmed by the Supreme Court in United States v. Ansonia Brass and Copper Go., supra, that, as between the United States and the supply lien creditors of the Wm. R. Trigg Company, the latter had *274priority of lien upon the “Mohawk” and the “Galveston.” Since the final settlement of that question the supply lien creditors have all been satisfied.
The present controversy involves the right of the United States to preference over the general creditors of the Wm. E. Trigg Company in favor of certain contractual liens held by them against the “Mohawk” and the “Galveston.”
These two vessels were built by the Trigg Company under contracts with the United States, which provided for a lien upon each vessel in favor of the government for all moneys advanced by it on account thereof during the progress of the work.