The plaintiff instituted this action to recover from the defendant the sum of $1,016.75, alleged to be due for electricity furnished for lights and power during the months of May, June and July of the year 1915, at its special instance and request. The respondent admits the use and consumption of the electricity as alleged, but contends that said electricity was fur*100nislied and was used, under a contract entered into between the parties hereto in the year 1910, under and' by the terms of which the amount due was $494.50, which amount respondent duly tendered to appellant, when due.
The ease was tried in the district court on an agreed statement of facts, from which it appears:
1. That on the third day of December, 1909, appellant and respondent entered into a written contract by the terms of which the appellant agreed to furnish to the respondent “all the electric current the railway company may require for lighting and power purposes at its pumping station — approximately two and a half miles west of the Northern Pacific Passenger Station, and at its roundhouse, machine-shop, ear-shop, coal dock, passenger and freight stations, lunch-room, offices and other buildings and premises at Helena, Montana.”
2. This contract or agreement was to continue in force for a term of five years from the date of the installation of the secondary lighting and power systems of the company, which installation was not completed until April 30, 1910.
3. The contract further provided that the railway company reserved the right, at its option, upon giving the power compány thirty days’ written notice prior to the expiration of the contract, “to renew the same for an additional period of five years. ’ ’
4. The rates fixed by the contract for electric current for power and light were about one-third the regular rates in effect in the months of May, June and July, 1915.
5.