United States Court of Claims December 7, 1925, No. A-188 (Weller Construction Co. v. United States)
Also known as
United States · · · 07-12-1925
Hay, Judge,
delivered the opinion of the court:
The facts are fully set forth in the findings and it is not necessary to recapitulate them here.
The first item claimed by the plaintiff is the sum of $4,704.24, which amount the plaintiff expended in the proper care of the materials and property of the United States as *269a necessary result of the stoppage of the work by the United States.