Michigan Supreme Court March 4, 1958, Docket 43, Calendar 47,171 (Huron Portland Cement Co. v. Public Service Commission)
Also known as
United States · · · 04-03-1958
Smith, J.
The problem presented concerns the furnishing o'f electric service to the appellant. This
*257
is an appeal in the nature of certiorari from an order of the Michigan public service commission dated January 4, 1957, “but only insofar as it denies in paragraph 4 of the order section thereof the petition of Huron Portland Cement Company for direct electric service from Consumers Power
Read the full text