United States Court of Claims October 8, 1958, No. 116-52 (Carman v. United States)

Also known as

United States · · · 08-10-1958

LittletoN, Judge,

delivered the opinion of the court:

Plaintiff seeks to recover additional compensation for extra work performed in reclearing certain areas in connection with its contract to clear an area in the vicinity of the Heyburn Dam Project.