United States Court of Claims April 8, 1959, No. 234-53 (A. S. Schulman Electric Co. v. United States)
Also known as
United States · · · 08-04-1959
Opinion
per curiam:
This is a suit for increased costs under a Government contract. The increased costs are -claimed to have resulted from delays occasioned by the defendant’s failure to give effective notice to proceed, as required by the terms of the contract.
The facts upon which plaintiff relies are substantially the same as those in the case of Abbett Electric Corporation v.