District Court, D. Oregon December 12, 1959, Civ. No. 9433 (McKinnon v. United States)

Also known as

United States · · · 12-12-1959

SOLOMON, Chief Judge.

Plaintiff brought this action against the United States under the Tucker Act, 28 U.S.C.A. § 1346(a) (2), to recover $9,999.99.1 Plaintiff claims this amount as compensation for extra work done for the Bureau of Reclamation, Department of Interior, under Contract No. 12r-19806.

Plaintiff completed his contract for enlarging and improving the Lost River channel in Oregon. The river channel between stations 375 and 274 required reconstruction to a centerline ten feet to the right or east of the centerline of the old channel.

From station 375 to station 370, plaintiff used two draglines, putting more ma*914terial on the east bank than on the west bank for the reason that more material was removed by the east dragline. The west bank was also slightly below 18 feet in height. At this point the resident engineer instructed plaintiff to equalize the banks and make them a minimum of 18 feet high.

Subsequent to these instructions, the Government issued revised Drawing No. 12-D-821 showing the banks equalized at a minimum of 18 feet. The letter accompanying the revised drawing asserted that the drawing did not change the contract specifications. Plaintiff made timely, written protest to this assertion as the basis for claiming additional compensation.

The Government’s Contracting Officer denied plaintiff additional compensation for such work, and the Interior Board of Contract Appeals affirmed. Thereafter, plaintiff filed this action.

Plaintiff asserts that he is entitled to a trial de novo in this court. The Wunderlich Act (41 U.S.C.A.