Supreme Court of the United States December 3, 1962, 48 (Federal Power Commission v. Tennessee Gas Transmission Co.)

Also known as

United States · · · 03-12-1962

Mr. Justice Clark

delivered the opinion of the Court.

This case involves the authority of the Federal Power Commission after hearing to order an interim rate reduction as well as a refund of amounts collected in excess thereof where a portion of a previously filed increased rate is found unjustified but the remainder of the proceeding is deferred.