Court of Appeals of Kentucky June 28, 1963 (Walker v. Valley Plumbing, Inc.)

Also known as

United States · · · 28-06-1963

PALMORE, Judge.

By written contract dated May 7, 1957, one R. E. Pearson agreed to construct a home for the appellants, Jack Walker and wife, and convey it to them on completion. The work was completed early in July and the transaction was closed on July 8, 1957, by payment of the balance of the purchase or contract price and conveyance of the property to the Walkers. When the Walkers moved into the new home on September 9, 1957, they discovered that the outside water faucet was connected to the hot water and the dishwasher was connected to the cold water only. After an unsuccessful attempt to secure corrective action through Pearson they ascertained that Valley Plumbing, Inc., the appellee, had done the plumbing work and thereupon contacted Valley, which proceeded to correct the defect during the first week of October, 1957.

Unbeknown to the Walkers when the correctional work was ordered by them and done, Valley had not been paid by Pearson and was owed $1395 for the plumbing job on the house. Pearson had given to the Walkers at the time of closing on July 8, 1957, an affidavit that all laborers, material-men and subcontractors had been paid in full. Valley had neither filed in the county clerk’s office a statement pursuant to KRS 376.010(2) that it had furnished or expected to furnish labor or materials, nor had it notified anyone pursuant to KRS 376-010(3) of its intention to hold the property liable for its claim. But on December 11, 1957, within 75 days after doing the slight additional work in October of 1957, Valley did proceed to notify the Walkers and record a statement of its lien claim. This was the first actual notice to the Walkers that Valley had not been paid.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.