On the 26th day of September, 1955, the New York State Thruway Authority entered into an Engineering Agreement, H. C. 3559-A, with Charles H. Sells, Inc. The agreement provided for the supervision and inspection of the construction of a portion of the Erie Section of the Thruway and the contract to be supervised was E. T. 55-8, S. T. 55-10, B., C. 55.72; the contractor was Yonkers Contracting Co., Inc.
The agreement with the claimant was negotiated and not a bid contract, with the Yonkers Contracting Co., Inc., contract available during the negotiations. The claimant was to perform the same functions that a State Engineer would perform. The Yonkers. Contracting Co., Inc., contract was incorporated by reference into the claimant’s agreement.
The engineering agreement provided that claimant was to receive 4%% of the complete and final construction cost, excluding, however, costs of acquisition of right of ways, work performed by public utility companies and services performed by the New York State Thruway Authority. In accordance with the final tabulation by the New York State Thruway Authority, claimant was entitled to receive $17,056.14. Claimant contended that the New York State Thruway Authority had granted extensions to Yonkers Contracting Co., Inc., compelling it to expend additional time on the site at additional costs to it and seeks to recover $100,462.80.
Claimant refused payment of $17,056.14, since it would be required to sign a waiver releasing the New York State Thruway *634Authority. After the claim was filed, a severance motion was made by claimant and a judgment granted reserving the question of the right to interest on the retained percentage for this trial.
The instant claim is for the additional services performed by the claimant due to extensions of time granted by the New York State Thruway Authority and the question of interest on the retained percentage.