Court of Appeals for the Fourth Circuit May 3, 1968, No. 11631 (United States v. Glassman Construction Co.)
Also known as
United States · · · 03-05-1968
CRAVEN, Circuit Judge:
The question, correctly framed by the district judge, is whether a supplier of materials, who has not in fact been fully paid, can recover under the Miller Act, 40 U.S.C. § 270b, the balance due when it has received and endorsed checks from the general contractor that were more than sufficient to cover that balance.
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit