District of Columbia Court of Appeals February 6, 1970, 4759 (District of Columbia v. Heman Ward, Inc.)
Also known as
United States · · · 06-02-1970
KELLY, Associate Judge.
The July, 1957 contract in which Heman Ward, Inc. (hereinafter Ward) agreed to build two bridges for the District of Columbia assessed against the contractor liquidated damages of $150 for each day that the job exceeded the completion period of 360 calendar days.