Appellate Court of Illinois November 30, 1981, 79-1659 (M. A. Lombard & Son Co. v. Public Building Commission)
Also known as
United States · · · 30-11-1981
Mr. JUSTICE WILSON
delivered the opinion of the court:
M. A. Lombard & Son Company (Lombard) appeals from a judgment of the trial court in favor of the Public Building Commission of Chicago (Commission). Lombard presents two issues for review: (1) that it is fraudulent for a public body to advertise for bids knowing that the. construction plans are incomplete and later make material departures in the plans and specifications; and (2) the “no damage for delay” clause does not absolve a public body under all conditions and circumstances. The pertinent facts follow.
Lombard submitted the lowest bid of $8,794,000 in accordance with certain plans and specifications, and was awarded the general works contract from the Commission on December 14,1971, for construction of the Archer-Pulaski High School. The contract encompassed the construction of two buildings: building “A” to be completed in 360 days or by December 28, 1972, and building “B” to be completed in 420 days or by March 7,1973.
Prior to the general contract, there were preliminary contracts awarded to prepare the site for construction. George Lombard, president of Lombard, testified Lombard was aware of the prior contracts as well as the contractual provisions concerning changes in the work and delays.
At a meeting on December 21, 1971, Fred Coleman, the project manager for the joint venture, informed George that Lombard was going to get a notice to proceed on December 28, 1971. George informed him that the job site was not ready and asked that the day of the notice to proceed be extended to some future date. However, the notice to proceed was given on December 28,1971.
Lombard exhibits indicated that there were numerous charges made throughout the contract period in the drawings and specifications. Lombard contends that Bulletin No. 2, dated March 24, 1972, materially changed the bid drawings with the issuance of construction drawings and additional compensation in the amount of $221,871.40 was authorized.