Court of Appeals for the D.C. Circuit December 11, 1981, Nos. 80-1334, 80-1527 (Anaheim v. Federal Energy Regulatory Commission)
Also known as
United States · · · 11-12-1981
Opinion for the Court filed by Circuit Judge WALD.
WALD, Circuit Judge:
The Federal Power Act regulates “the sale of electric energy at wholesale in interstate commerce,” 16 U.S.C. § 824, and requires rates to be “just and reasonable,” 16 U.S.C. § 824d, i.e., ample to allow recovery of a utility’s operating costs and a fair rate of return on capital investment. See, e.g., Public Systems v. FERC, 606 F.2d 973, 978 n.24 (D.C.Cir.1979). The only costs recoverable under federal rates are those allocable to the wholesale transactions, subject to federal jurisdiction, and not those allocable to retail sales, regulated by the state. See 16 U.S.C. § 824(b). In these consolidated appeals, we review two orders1 of the Federal Energy Regulatory Commission (“FERC” or “Commission”) which approved increases in wholesale electric power rates of Southern California Edison Company (“Edison” or “Company”). In No. 80-1527, Edison urges that FERC (1) set an unreasonably low rate of return, (2) understated the Company’s rate base by excluding non-cash expenses from the working cash allowance, and (3) improperly disallowed recovery of certain operating costs. In No. 80-1334, five California cities (“Cities”)2 assert that the approved rate erroneously allowed Edison (1) to charge wholesale customers for ojjerating costs associated exclusively with retail transactions subject to state regulation, and (2) to recover from wholesale customers a portion of losses stemming from a retail fixed-rate contract. For the reasons set forth below, we reject the contentions of petitioners in each case and affirm the Commission’s actions.
I. BACKGROUND
The Cities, wholesale-for-resale customers of Edison, operate publicly-owned utilities which distribute electricity to retail customers within and near their respective jurisdictions. On October 31, 1975, Edison filed *4with the Federal Power Commission3 an increase in its wholesale rates and, as required by Commission regulations, 18 C.F.R. § 35.
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit