United States Court of Claims July 1, 1981, No. 225-74 (American Ship Building Co. v. United States)

Also known as

United States · · · 01-07-1981

NICHOLS, Judge,

delivered the opinion of the court:

The issues presented in this breach of contract case are (1) whether a contract requirement that performance be completed within 900 days is an affirmative representation or warranty by the government that the contract could, in fact, be completed within the stated time, and (2) whether the government’s failure to disclose superior knowledge of