United States Court of Claims September 23, 1981, No. 555-79C (Brookfield Construction Co. v. United States)
Also known as
United States · · · 23-09-1981
DAVIS, Judge,
delivered the opinion of the court:
The Contract Disputes Act of 1978, Pub. L. No. 95-563, 92 Stat. 2383, 41 U.S.C. 601 et seq. (Supp III, 1979) — in its summary transitional provision for the interim between, on the one hand, complete non-coverage by the new statute of government contracts, and, on the other, full prospective coverage for wholly new agreements made after the Act became law — presents numerous problems of interpretation.1 These are transient, of course, but many of them are important for both contractors and Government. The present case falls into that class. It involves a pre-Act agreement and contract-claims filed with the contracting officer years before the March 1, 1979 effective date of the Act, but decided by the contracting officer after the Act went into operation. The several questions before us all concern interest on the claim-awards. The chief of these issues is whether a contractor which has elected to proceed under the Act may recover interest on its subsequently-allowed claims for periods of time prior to the effective date of the Act. We hold that the Act does not allow such retroactive interest, and that plaintiffs recovery is limited to simple, variable-rate interest running from the effective *553date of the Act (March 1,1979) until December 13,1979, the date of payment of the underlying claims.
I
The case is here on cross-motions for summary judgment, and the facts are not in dispute. Under the 1965 contract on which this action is based, plaintiff joint venture2 agreed to construct a hurricane barrier for the United States Army Corps of Engineers for the fixed price of $8,083,075. During the course of construction (April 1965-October 1968) plaintiff experienced various changes, changed conditions and suspensions of work which eventually resulted in the submission of approximately 42 claims for equitable adjustments. Most of the claims were settled and paid, and modifications issued, before March 1, 1979.
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit