Bedford County Circuit Court December 21, 1981 (Stone v. Bedford County School Board)
Also known as
United States · · · 21-12-1981
By JUDGE WILLIAM W. SWEENEY
The sole issue in this case is whether the Bedford County School Board breached its contract with the plaintiff, a teacher, by its failure to give him notice of a contract change for the 1980-81 school year by April 15, 1980. The case was heard on stipulations and two days of testimony.
I find that the plaintiff is a continuing contract teacher employed by the Bedford County School Board. The contract provides that his services were to begin on July 1, 1976, "and thereafter as prescribed by the School Board." (Exhibit A-l). It further provides that the Board is not obligated under the contract "unless and until sufficient funds to meet its obligations hereunder have been approved by the appropriating body." The appropriating body in this case is the Bedford County Board of Supervisors. In addition, the contract provides that "the annual period of service shall be fixed by the School Board in accordance with law."
In addition to the continuing contract, the parties entered into salary agreement contracts each year (Exhibits *461B1-B5). The agreements specified the plaintiff’s salary, his period of service, and the school to which he was assigned. Each agreement was tendered to the plaintiff after April 15 th of the respective school year and was signed by him in June. Separate contracts were executed for each school year. Under the salary agreement signed by the plaintiff in June 1979, his annual period of service for the 1979-80 school year was set at 12 months. For a number of years, he had been a 12-month contract teacher.
In the Spring of 1980, the County Board of Supervisors consisted of many newly elected members.