Appellate Division of the Supreme Court of the State of New York December 5, 1985 (Dierks Heating Co. v. Egan)

Also known as

United States · · · 05-12-1985

Casey, J.

Appeal from a judgment of the Supreme Court at Special Term (Pennock, J.), entered April 23, 1985 in Albany County, which dismissed petitioner’s application, in a proceeding pursuant to CPLR article 78, to review a determination of the Office of General Services to forfeit petitioner’s bid deposit.

Petitioner, a heating, ventilating and air conditioning contractor, submitted the lowest bid of $583,565, together with a bid deposit of $21,000, to the Office of General Services (OGS) in connection with the construction of the State Police Troop L Headquarters in the Village of Farmingdale, Nassau County. Petitioner was so informed and was also told that the next lowest bid was $739,777, or $156,212 greater than petitioner’s bid. This disparity caused petitioner’s president to review the OGS specifications and he then ascertained that petitioner had failed to include in its submitted bid the cost of temporary heat and fuel, as required by the specifications, because the construction was a new building which lacked a preexisting heating system. Petitioner admits that its failure to include this item was negligence on its part. Despite this admission, however, and contrary to the instructions with which it was furnished permitting the withdrawal of bids only if the bidder made a verified error in its computation, petitioner requested OGS to release it from the bid.

OGS granted petitioner a "mistake hearing”. At this hearing, petitioner claimed that it attempted to establish that its bid would have been $182,533.60 greater if it had considered temporary heat as a specification and that OGS was so informed. OGS claims that petitioner’s bid would have been only $70,300 higher and, based on this figure, concluded that the net loss to petitioner after deducting overhead and profit would be $31,669. Following the hearing, OGS refused to release petitioner from its bid because its error was a negligent omission and not an arithmetic error in computation.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.