West Virginia Court of Claims December 3, 1985, CC-82-200 (Carl M. Geupel Construction Co. v. Department of Highways)

Also known as

United States · · · 03-12-1985

PER CURIAM:

Claimant, Carl M. Geupel Construction Company, Inc. entered into a contract with the respondent, West Virginia Department of Highways, designated as Project 1-79-1(14)21, for the construction of a section of 1-79 in Ro.ane County, West Virginia. Notice to proceed was given to the claimant on May 7, 1970, and the scheduled completion date was September 30, 1972. Claimant experienced several delays during construction when slides occurred on the project. The delays resulted in an actual completion date for the project in October, 1974. This two-year delay resulted in alleged damages to claimant in the amount of $577,068.35, for which this claim was filed.

The first major delay occurred during the summer of 1970 when a partially completed embankment section suddenly slid as a result of a foundation failure. Several months elapsed before respondent instructed claimant as to required correction work which could not be done in the winter months. Further foundation failures occurred throughout the construction of the embankment which was not completed until March, 1972.

The respondent was required to redesign the foundation undercut in another area of the project resulting in further delay to claimant.

The longest delay on the project occurred when the project supervisor for the respondent ordered claimant to cease work in an area where *27bedrock was not encountered at the elevation shown on the plans. Various circumstances delayed the preparation of the revised drawings by the respondent. Once the change order for the work was prepared, an additional delay was experienced because the respondent had not acquired the right-of-way needed for the revisions. As a result of these delays, the corrective work could not begin until January of 1973.

The claimant and respondent stipulated that there were numerous slides which had an impact on the time required for the construction of the project.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.