Aliceville Hydro Associates (“AHA”) petitions this court for review of two orders of the Federal Energy Regulatory Commission (“FERC” or “Commission”) rejecting as untimely AHA’s application for a preliminary permit to construct a hydroelectric plant at the Aliceville Lock and Dam in Pickens County, Alabama. As a result of FERC’s action, it is probable that a license authorizing hydroelectric development of the Aliceville site will ultimately be granted to intervenor Independence Electric Corporation (“IEC”), which also filed a preliminary permit application for the site.

FERC concluded that AHA’s application was untimely because it was filed on the day that the Commission had specified for Commission acceptance of the surrender of a previously issued permit for the Aliceville site. FERC reasoned that, under the Commission’s Rules of Practice and Procedure, the previously issued permit remained in effect until the close of Commission business on the date specified for surrender and that AHA’s application was therefore premature. In this appeal, we must decide whether the Commission reasonably interpreted its Rules of Practice and Procedure and its Notice accepting surrender of the previously issued permit. We must also decide whether the fact that on other occasions and under similar circumstances FERC staff members have accepted applications for preliminary permits entitles AHA to exemption from the Commission’s interpretation of its rules. For the reasons stated below, we affirm the Commission's orders.

I. Statutory and Regulatory Framework

FERC is authorized by the Federal Power Act to regulate the development of hydroelectric power on federal property and on bodies of water subject to federal jurisdiction. 16 U.S.C. § 797 (1982). The Commission exercises this authority by issuing licenses for the construction, operation, and maintenance of facilities necessary for such development.

Id.

§ 797(e).