United States Court of Claims December 31, 1986, No. 102-86C (Malissa Co. v. United States)
Also known as
United States · · · 31-12-1986
ORDER
SMITH, Chief Judge.
(1) Upon consideration of the defendant's Motion to Dismiss, or in the Alternative, Motion for Summary Judgment, it is ordered as follows:
(a) The defendant’s motion is denied as to the plaintiff’s claim in the amount of $33,018.00. The July 10, 1985, letter from the plaintiff to the contracting officer satisfies the Contract Disputes Act (CDA), 41 U.S.C. § 605(a) requirement that a written claim be submitted requesting a final decision. The letter clearly identified the amount of monetary compensation requested, stated that it wanted the matter resolved within 60 days and precipitated the contracting officer issuing a final decision on September 6, 1985.
Prior to the July 10, 1985 letter, the plaintiff had requested a final decision by letter dated December 12, 1981. The court having decided the July 10, 1985, letter to be a valid claim declines to rule on the validity of the December 12, 1981, letter, except to note the court does not follow the holding in Pathman Construction Co. v. United States, 10 Cl.Ct. 142 (1986), appeal docketted, Appeal No. 86-1537 (Fed.Cir. July 30, 1986).
In Pathman one of the most learned and scholarly members of this court found that the failure of the contracting officer to issue a decision within 60 days of the claim triggered the 12 month statute of limitations in 41 USC § 609(a)(3). In analyzing four prior decisions of this court on this matter my colleague correctly found a significant division of rationale for these decisions. See LaCoste v. United States, 9 Cl.Ct. 313 (1986); Turner Construction Co. v. United States, 9 Cl.Ct. 214 (1985); Vemo Co. v. United States, 9 Cl.Ct. 217 (1985); G & H Machinery v. United States, 7 Cl.Ct. 199 (1985). As a body of law, they provided no single coherent reason for not applying the 12 month statute of limitations, once the contracting officer has failed to reach a decision within 60 days.