Indiana Court of Appeals June 26, 1989, No. 61A01-8811-CV-349 (Indiana Utility Regulatory Commission v. Citizens Action Coalition of Indiana, Inc.)
Also known as
United States · · · 26-06-1989
ROBERTSON, Judge.
This is an appeal from a mandamus action commenced by the appellees, Citizens Action Coalition of Indiana, Inc., the city of Terre Haute, and Save the Valley, Inc. (collectively referred to as the Coalition), in the Parke Cireuit Court,. The issue we consider is whether the Parke Circuit Court had jurisdiction to issue an order directing the Indiana Utility Regulatory Commission (Commission) to hold a hearing on the Coalition's petition for a permanent reduction of rates for customers of Public Service Indiana (PSI). We conclude the Parke Circuit Court did not have jurisdiction to so order.
At the time the Coalition filed its petition for a permanent electric rate reduction with the Commission in October, 1987, the Commission and PSI were operating pursuant to an order of the Commission issued March 7, 1986 which established emergency rates for a four-year period ending December 31, 1989 and, among other things, directed PSI to file in 1989 for the establishment of permanent retail electric rates. Before any action had been taken by the Commission on the Coalition's petition, PSI requested a modification of the 1986 order setting emergency rates. The Commission added the appellees as intervenors to the proceedings brought by PSI, dismissed the proceedings brought by the Coalition, and directed its staff to investigate the reasonableness of PSI's rates and charges. The Coalition did not appeal the dismissal of its petition; neither did it refile its petition under the new cause number.
The matter proceeded to a prehearing conference at which the Commission determined it would engage in a bifurcated investigation, addressing first PSI's continued need for an emergency rate schedule, and then, subsequently, a permanent rate schedule. After eight days of hearings in which the Coalition fully participated, the Commission found it premature to begin a permanent rate investigation because circumstances warranting emergency action continued to exist.
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit