Texas Court of Appeals, 9th District (Beaumont) August 30, 1990, 09-89-063 CV (Mar-Len of Louisiana, Inc. v. Gorman-Rupp Co.)

Also known as

United States · · · 30-08-1990

OPINION

WALKER, Chief Justice.

This is a suit by appellee, The Gorman-Rupp Company (hereinafter referred to as “Gorman-Rupp” or appellee) against appellant, Mar-Len of Louisiana, Inc. (hereinafter referred to as “Mar-Len” or appellant) for breach of contract. The breach of contract claim is in connection with a purchase order submitted by Mar-Len to Gor-man-Rupp. The purchase order is in re

*882

gard to the manufacture and supply of certain goods, including pumps and control devices, which were to be utilized in the construction of five (5) transfer stations for a waste treatment facility for the City of DeRidder, Louisiana. Mar-Len was the general contractor on a portion of the waste treatment project.

As reflected by plaintiffs first amended original petition, Gorman-Rupp also sued Safeco Insurance Company of America (hereinafter referred to as “Safeco”) in connection with the payment and/or performance bonds which were required to be procured by Mar-Len in connection with the project. Mar-Len and Safeco responded to Gorman-Rupp’s allegations by asserting a general denial together with certain affirmative defenses. In particular, Mar-Len and Safeco affirmatively asserted that all conditions precedent to plaintiffs recovery had not occurred or had not been satisfied.

On October 10, 1988, this action proceeded to trial before a jury in the 136th Judicial District Court, Honorable Jack King presiding. At the close of plaintiff’s evidence, Mar-Len and Safeco asserted their motions for directed verdict. The trial court took such motions for directed verdict under consideration for a later ruling. Upon the close of all the evidence, Mar-Len and Safeco re-urged their motions for directed verdict. The trial court again took same under consideration. On October 13, 1988, the jury returned a ten (10)-two (2) verdict in favor of appellee.

Thereafter, Mar-Len and Safeco filed with the trial court their motion for judgment non obstante veredicto, and motion for judgment.

Read the full text