Court of Appeals for the Third Circuit March 7, 1990, 89-5362, 89-5660 and 89-5661 (James D. Mesalic v. Fiberfloat Corp. D/B/A Harley Boat Company, Howard D. Harley, Individually, Jointly and Severally)

Also known as

United States · · · 07-03-1990

OPINION OF THE COURT

A. LEON HIGGINBOTHAM, Jr., Chief Judge.

Appellant, James D. Mesalic (Mesalic), appeals from a final order of the United States District Court for the District of New Jersey dismissing this diversity complaint for lack of in personam jurisdiction over the appellees, Howard Harley (Harley) and Fiberfloat Corp., d/b/a Harley Boat Company (Fiberfloat). 708 F.Supp. 641.

1

We will reverse the district court’s order.

I.

Mesalic is a New Jersey citizen. The president of Fiberfloat, Howard Harley, is a citizen of the State of Florida. Fiberf-loat, a Florida corporation with its principal place of business in Bartow, Florida, advertises its products for sale in

Boating,

a magazine aimed at a national audience.

Boating

is not directed specifically to New Jersey residents. However, at oral argument, appellees conceded that the magazine was distributed in New Jersey. Because Fiberfloat has no showrooms or distribution network in New Jersey, Mesalic went to its manufacturing facility in Bar-tow, Florida to purchase a boat. Harley quoted a price for Mesalic and the next day, he signed a contract to purchase a 42-foot custom built, luxury power boat. The purchase was conditioned upon Mesalic’s satisfaction with a sea trial of the same model boat. The sales agreement was silent as to which state’s law would govern interpretation of the contract. However, the warranty gives Fiberfloat the right to require the customer to deliver the vessel to Fiberfloat’s facility in Florida for repairs.

2

The total cost of the boat was approximately $235,000 including $1,650 for delivery.

After conducting a trial run, Mesalic made a down payment and Fiberfloat began construction of his boat. While the boat was under construction, Mesalic made several trips to Florida to inspect the construction and to make progress payments. At other times, however, the parties communicated by mail and by telephone.