United States Court of Claims May 13, 1992, No. 90-75C (Isles Engineering & Construction, Inc. v. United States)
Also known as
United States · · · 13-05-1992
ORDER
MOODY R. TIDWELL, III, Judge:
This case is before the court on defendant’s motion to dismiss. Defendant alleged that plaintiff failed to comply with the certification requirements of the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (1988) (CDA), and consequently plaintiff’s complaint should be dismissed for lack of subject matter jurisdiction.
FACTS
On September 30, 1986, the United States, acting through the Department of the Navy, awarded a firm-fixed price contract to plaintiff, Isles Engineering & Construction, Inc. (Isles), in the amount of $234,000.00. Isles was to unearth, repair, and rebury certain water mains, valves, and hydrants at Kingsville Naval Air Station, Kingsville, Texas. The Navy provided Isles with plans, supplied by the Navy’s *241contract architect-engineer, which purported to identify the location of the buried mains and valves. The Navy issued a Notice to Proceed on October 14, 1986, and all work was to be completed by February 12, 1987.
The project was delayed because certain pipes could not be found in the locations indicated on the contract drawings, while other pipes were found that were not shown on the drawings. Delays also arose because valves that were needed to cut-off water to certain pipes were not closed in a timely fashion. The contract was substantially completed on April 17, 1987.
Between March and May, 1987, Isles submitted forty-two requests for equitable adjustment totalling $64,063.57 for extra work associated with changes and delays it encountered in performance. Attempts to reach a negotiated settlement of the claims were unsuccessful. On August 14, 1987, the Navy issued unilateral modification P00003 for “unforseen conditions encountered while repairing water mains,” which increased the contract price by $28,515.54, and increased the performance time by 17.3 days. On the same day, the Navy issued modification P00004 which increased the performance time by nineteen days due to weather delays.