Court of Appeals for the Ninth Circuit June 30, 1992, Nos. 88-6409, 88-6410 (Mai Steel Service Inc. v. Blake Construction Co.)

Also known as

United States · · · 30-06-1992

DAVID R. THOMPSON, Circuit Judge:

This appeal challenges a district court ruling that appellant Molnick’s Inc., a steel installer on a federal construction project, cannot recover under either the prime contractor’s Miller Act payment bond or the subcontractor’s common law payment bond for its increased labor and material costs attributable to construction delays. We have jurisdiction under 28 U.S.C. § 1291 and we reverse. We also conclude that the prime contractor’s surety is entitled to indemnification from the subcontractor’s surety to the extent of its liability for Mol-nick’s additional costs.

FACTUAL BACKGROUND

The Department of the Navy hired Blake Construction Company to build a naval hospital in San Diego, California. Pursuant to the Miller Act, 40 U.S.C. § 270a-270d, Blake obtained two Miller Act bonds from Aetna Casualty Insurance. One bond guaranteed Blake’s performance under its contract with the United States government. The other bond guaranteed pay*416ment to all persons supplying labor or materials to the project.1

Blake subcontracted with Mai Steel Services to fabricate and install the hospital’s steel framework. Mai furnished a performance bond for $6,940,000, guaranteeing the satisfactory completion of the framework. It also provided a payment bond for the same amount. Commercial Union Insurance was the surety on both bonds.

Blake also subcontracted with Molnick’s to install the hospital’s steel decking. Under the terms of this subcontract, Molnick’s was required to finish the decking no more than six months after the framework was in place.

Mai entered into a sub-subcontract with Molnick’s. This sub-subcontract obligated Molnick’s to assume all responsibility for installing the hospital’s framework. Mol-nick’s was given five months to finish the task. Molnick’s conditioned its performance on Mai’s ability to supply it with steel and other materials according to a predetermined schedule.

Mai never lived up to its part of the sub-subcontract.