Appellate Division of the Supreme Court of the State of New York November 22, 1995 (Justin Electrical, Inc. v. Board of Education of Shenendehowa Central School District)

Also known as

United States · · · 22-11-1995

—Casey, J.

Appeal from an order of the Supreme Court (Viscardi, J.), entered October 13, 1994 in Saratoga County, which denied defendant’s motion to dismiss the complaint as time barred.

At issue on this appeal is whether plaintiff’s breach of contract action against defendant should be dismissed for lack of compliance with the Education Law § 3813 notice of claim requirement. Supreme Court denied defendant’s motion to dismiss, concluding that a question of fact existed as to whether plaintiff’s notice of claim was filed within 3 months of the accrual of the claim. We agree and, therefore, affirm the order.

*837In actions of this nature, the claim accrues for the purpose of the notice of claim requirement when the contractor’s damages become ascertainable (see, Matter of Board of Educ. [Wagner Constr. Corp.], 37 NY2d 283, 290). It is generally recognized that damages are ascertainable once the work is substantially completed or a detailed invoice of the work performed is submitted to the school district (see, Matter of Board of Educ. [Merritt Meridian Constr. Corp.], 210 AD2d 854, 856; G.A. Constrs. v Board of Educ., 176 AD2d 856, 857). Defendant contends that the work was substantially completed on August 18, 1992, the date listed in the certificate of substantial completion prepared by the project engineer and signed by the parties. As noted by Supreme Court, the project engineer did not prepare the certificate until November 1992 and backdated the substantial completion date. The certificate referred to the completion of the entire project sufficient to permit defendant’s occupancy and did not, in our view, necessarily establish that plaintiffs electrical work was substantially completed for the purpose of determining whether its damages were ascertainable.

Evidence in the record demonstrates that plaintiff continued to perform electrical work long after August 18, 1992 and continued to receive periodic payments which were substantial.