Court of Appeals for the Seventh Circuit November 14, 1995, 94-3533 (Hm Holdings, Incorporated v. Sharyn L. Rankin, as Personal Representative of the Estate of Robert S. Rankin, Deceased)

Also known as

United States · · · 14-11-1995

CUMMINGS, Circuit Judge.

In September 1990 plaintiff HM Holdings, Inc. (“Seller”) filed a complaint in the district court to foreclose a land contract between its predecessor and Robert S. Rankin (“Buyer”).

1

After the Buyer filed an answer and counterclaim in October 1990, Seller moved to dismiss the counterclaim and for entry of judgment on the pleadings. In August 1992 the district court granted Seller’s motions but also simultaneously granted Buyer an opportunity to replead the counterclaim and answer.

In September 1992 Buyer filed an amended answer and amended counterclaim. The following month Seller moved to dismiss the amended counterclaim and for judgment on the pleadings. These motions were granted in April 1994 and trial was set on the issue of damages only. In September 1994 the district court entered judgment for foreclosure and sale against Buyer and also a personal money judgment for Seller in the amount of $687,332.97, resulting in this appeal.

I.

Facts

In its complaint to foreclose a land contract against Buyer, Seller alleged that the lawsuit arose out of an installment sale contract entered into on December 24, 1986, between Seller’s predecessor in interest, SCM Corporation, Inc. (“SCM”) and Buyer. Under the contract SCM agreed to sell and Buyer agreed to purchase industrial property at 1717 Summer Street, Hammond, Indiana. The purchase price of $500,000 was to be paid in monthly installments of $3,938.96 for 36 months beginning in February 1987, with the final installment of $358,782.20 to be paid in January 1990.

In January 1990, at Buyer’s request, Seller agreed to amend the contract to provide for a seven-month extension of the January 1, 1990, due date of the balance of the purchase price. During this extension, Buyer was to make six additional installment payments to retire the outstanding principal and interest balance due under the contract by June 30, 1990.