Appellate Division of the Supreme Court of the State of New York March 4, 1996 (Shroid Construction, Inc. v. Dattoma)

Also known as

United States · · · 04-03-1996

The Supreme Court erred in its calculation of damages resulting from the defendant’s illegal three-day work stoppage. The plaintiff established at the hearing, through the uncontroverted testimony of its vice-president, that with respect to the three-day work stoppage on February 3, 6, and 7, 1989, it suffered $15,414.12 in losses.