United States Court of Federal Claims June 12, 1996, No. 95-489C (Joe Lemoine Construction, Inc. v. United States)
Also known as
United States · · · 12-06-1996
ORDER
MILLER, Judge.
This case is before the court on defendant’s motion for summary judgment. There are two issues to be resolved: 1) whether the contract required completion within 135 calendar days from the date of the contract award, regardless of when the contractor obtained the required performance bonds and the Government approved them; and 2) whether a bilateral modification changing the
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit