Court of Appeals for the Ninth Circuit December 21, 1998, No. 95-35883 (Taylor Construction Inc. v. ABT Service Corp. Inc.)

Also known as

United States · · · 21-12-1998

FERGUSON, Circuit Judge:

In this case, a Miller Act surety failed to pay a subcontractor the entire amount due under the bonded subcontract claiming that the Miller Act imposes no duty to pay the subcontractor the amount in the subcontract’s savings clause.

Read the full text