Court of Appeals for the Fifth Circuit July 17, 1998, 97-30699 (National Gypsum Company v. Oil, Chemical and Atomic Workers International Union Oil, Chemical and Atomic Workers International Union, Local 4-447)
Also known as
United States · · · 17-07-1998
BENAVIDES, Circuit Judge:
The district court granted summary judgment to the Oil, Chemical, and Atomic Workers International Union and its Local 4-447 on their motion to enforce an arbitration award and denied National Gypsum Company summary judgment on its motion to vacate that award. We affirm.
I.
On January 30, 1994, National Gypsum Company and Oil, Chemical, and Atomic Workers International Union Local 4-447 entered into a collective bargaining agreement (“the Agreement”), which covered nonsuper-visory production employees at National Gypsum’s plant in Westwego, Louisiana, from February 1, 1994, through February 1, 1997. Before September 1994, employees at the Company were scheduled to work seven: consecutive days each week with attendant overtime pay. Workers were paid time and a half on Saturdays and double time on Sundays. The seven-day work week had been in effect for 30 years at the Westwego plant. In the summer of 1994, however, the Company announced a “day-off’ program, effective in September 1994, under which no employee would work more than six days in any week. Although at first blush the day-off program might seem advantageous to the employees, the program resulted in the loss of overtime pay. Consequently, on September 1, 1994, the Union filed a grievance in which it complained that “[t]he company refuses to pay premium pay to the employees affected by the day off,” and that the refusal violated Article I, § 28 of the Agreement and any other provisions of the Agreement found to apply. Section 28 provides that “[n]o employee will be laid off
1
during the work week for the sole purpose of offsetting overtime worked during the week.” The parties were unable to resolve their dispute.
In June 1995, the Company demanded arbitration in accordance with Article X, § 69, which allows either party to request arbitration if more informal dispute resolution mechanisms fail., The parties agreed to bifurcate the liability .and damage portions of the arbitration.