PLAGER, Circuit Judge.
Promac, Inc. (“Promac”) was the lowest bidder for a contract with the Department of Veterans Affairs to construct a new medical research building. When performance was almost complete, Promac filed a claim for reformation of its contract based upon alleged violations of the Federal Acquisition Regulations by the Government in the bidding process. The Contracting Officer (“CO”) denied Promac’s claims. The Department of Veterans Affairs Board of Contract Appeals (“DVAB-CA” or “Board”) upheld the CO’s decision.
See Promac, Inc. v. VA Med. Ctr.,
1998 WL 780537, VABCA No. 5345 (VABCA Oct. 27, 1998). Because the Board did not err, we affirm.
BACKGROUND
In June of 1995, the Department of Veterans Affairs (“VA” or “Government”) issued an Invitation for Bids (“IFB”) for the construction of a 13,000 square foot research building at the VA’s Medical Center in Providence, Rhode Island. Although the VA’s Architect Engineering firm (“A/ E”) made a final estimate for the project
*787
of $3,075,000 with deductive alternates totaling $307,000, the IFB stated the cost of the project to be between $2 and $5 million. At the time the IFB was issued, the Medical Center in Providence had only received approval to spend $2,648,000 on the construction project.
The VA opened bidding on August 1, 1995. Seven firms returned bids ranging from $3,119,000 to $3,354,700. After bids were received, the A/E wrote to the CO that Promac’s bid was within 1% of the final cost estimate and that it was the A/E’s opinion that the VA had received a valid and fair low bid. According to Pro-mac, the Contracting Officer notified Pro-mac that it was the low bidder and that there was a funding problem. The CO allegedly told Promac that the VA was attempting to secure sufficient funds to make an award to Promac.
The VA Medical Center in Providence requested an increase in its budget for the project. That request, however, was not granted.