Supreme Court of New Hampshire November 17, 2000, No. 98-233 (New Hampshire Boring, Inc. v. Adirondack Environmental Associates, Inc.)

Also known as

United States · · · 17-11-2000

BRODERICK, J.

The plaintiff, New Hampshire Boring, Inc. (NH Boring), appeals the Derry District Court’s (Thornton, J.) dismissal of its breach of contract action against the defendant, Adirondack Environmental Associates, Inc. (Adirondack), on the basis of accord and satisfaction. We affirm.

The following facts were adduced at trial. NH Boring contracted with Adirondack to provide drilling services and materials at a site in New York. In August 1996, NH Boring sent Adirondack a bill for $79,561.00. In late December 1996, Adirondack responded in writing stating that if an “agreement” could be reached on the full amount due on the contract, it would promptly pay NH Boring $59,247.70. On January 7,1997, Adirondack again wrote to NH Boring, this time enclosing a check for $62,205.51. In its accompanying two-page letter, Adirondack detailed its accounting of the proper contract balance. At the conclusion of its correspondence, Adirondack stated that its check “fulfill[ed] all of [its] contractual agreements with [NH Boring].” The check itself contained no notation that it represented final payment.

NH Boring cashed the check without any limiting endorsement. It then applied the proceeds to its outstanding bill, noted a partial payment in its records, and issued a new invoice to Adirondack for the $17,355.49 balance. Adirondack refused to honor the invoice, and NH Boring filed suit. At the close of NH Boring’s case-in-chief, Adirondack successfully moved for a directed verdict on the basis of accord and satisfaction.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.