Court of Appeals of Washington May 29, 2001, No. 19224-5-III (Basin Paving Co. v. Mike M. Johnson, Inc.)

Also known as

United States · · · 29-05-2001

Sweeney, J.

A contractor may recover for a changed condition when it “could not reasonably have been anticipated by either party to the contract.” Bignold v. King County, 65 Wn.2d 817, 821-22, 399 P.2d 611 (1965). Mike M. Johnson, Inc., (MMJ) was awarded the contract for the Town of Lind’s wastewater and water system project.