TATEL, Circuit Judge:

Petitioners’ challenge the Federal Energy Regulatory Commission’s approval of Tennessee Gas Pipeline Company’s proposed method for awarding pipeline capacity and allocating meter amendments. Finding that the Commission engaged in reasoned decision making with respect to both issues, we affirm.

I.

The Natural Gas Act (“NGA”), 15 U.S.C. §§ 717, et seq., requires that natural gas companies charge “just and reasonable” rates for the transportation and sale of natural gas. Id. § 717c(a). To promote compliance with this mandate, the Act requires gas pipelines to file rate schedules *833with the Federal Energy Regulatory Commission and to notify the Commission of any subsequent changes in rates and charges. Id. § 717c(c), (d). On submission of a tariff revision, the Commission may hold a hearing to determine whether the pipeline has met its burden to show that the amended rates and charges are “just and reasonable.” Id. § 717c(e).

This case involves a proposed tariff revision that Tennessee Gas Pipeline Company (“Tennessee”) filed with FERC in 1996. In that revision, the company proposed adopting a net present value, or “NPV,” method to allocate pipeline capacity and to process so-called “meter amendments.” Two aspects of the revision are relevant here: whether Tennessee must impose a cap on the length of bids for pipeline capacity, and whether it must credit existing gas shippers’ contracts for mainline capacity in evaluating meter amendment’ requests. We considered both issues in Process Gas Consumers Group v. FERC (“PGC I”) and, finding FERC’s reasoning defective, remanded to the Commission for further proceedings. 177 F.3d 995, 997 (D.C.Cir.1999). Here, we explain each issue in turn, first outlining FERC’s original position, then summarizing our decision in PGC I, and finally describing the Commission’s orders on remand — the subject of this petition.