United States Bankruptcy Appellate Panel for the Eighth Circuit August 15, 2003, 03-6014, 03-6015 WM (Safeco Insurance Co. of America v. Farmland Industries, Inc. (In Re Farmland Industries, Inc.))

Also known as

United States · · · 15-08-2003

DREHER, Bankruptcy Judge.

The issue in these appeals is the scope of bankruptcy court jurisdiction. In each case the bankruptcy court dismissed in part Appellant’s claims on the ground that the court lacked jurisdiction to decide the dispute. For the reasons stated below, we reverse.

FACTS AND PROCEDURAL HISTORY

A. The Safeco/ADM Dispute

On May 4, 2001, ADM/Farmland, Inc. (“ADM”) purchased certain grain handling facilities from Debtor, Farmland Industries, Inc. (“Debtor”). The Purchase Agreement required Debtor to provide ADM with a bond indemnifying ADM against future environmental claims. Debtor purchased the bond (“the ADM bond”) from Appellant, Safeco Insurance Company of America (“Safeco”). The ADM bond, in the principal amount of five million dollars, was executed by Debtor and Safeco, as principal and surety respectively. It named ADM as obligee. The ADM bond had an effective date of May 4, 2001, and was renewable for four additional one-year periods unless Safeco gave ninety days notice of its intent to cancel or not to renew. The ADM bond further provided:

It is understood and agreed that [ADM] may recover the full amount of the Bond (less any previous amounts paid to [ADM] under the Bond) if [Safeco] cancels or nonrenews the Bond and, within twenty (20) days prior to the effective date of cancellation or nonrenewal, [ADM] has not received security acceptable to it to replace the Bond.

Safeco issued the ADM bond on the strength of two General Agreements of Indemnity (“the indemnity agreements”) that Debtor had executed and delivered to ADM in 1988 and 1993. Pursuant to these indemnity agreements Debtor agreed to indemnify Safeco should Safeco be required to make payment under any bond Safeco would write for Debtor.

On April 22, 2002, Safeco sent a Notice of Bond Cancellation to ADM, canceling the ADM bond effective July 26, 2002. Debtor filed for protection under Chapter 11 of the Bankruptcy Code on May 31, 2002.