New York Court of Appeals November 20, 2006 (Welsbach Electric Corp. v. MasTec North America, Inc.)
Also known as
United States · · · 20-11-2006
OPINION OF THE COURT
Rosenblatt, J.
For well over a century, parties to construction contracts in New York were permitted by decisional law and by statute to *627agree to “pay-if-paid” provisions. Agreements of that type create a condition precedent by which the subcontractor will not be paid unless the contractor has been paid. In 1995, however, we held in West-Fair Elec. Contrs. v Aetna Cas.