Court of Appeals for the D.C. Circuit May 8, 2009, 06-1426 (Alcoa Inc. v. Federal Energy Regulatory Commission)

Also known as

United States · · · 08-05-2009

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 20, 2009 Decided May 8, 2009

No. 06-1426

ALCOA INC.,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

On Petition for Review of Orders

of the Federal Energy Regulatory Commission

David R. Poe argued the cause for petitioner. With him

on the briefs were Sonia C. Mendonca and Brett A. Snyder.

Samuel Soopper, Attorney, Federal Energy Regulatory

Commission, argued the cause for respondent. With him on

the brief were Cynthia A. Marlette, General Counsel, and

Robert H. Solomon, Solicitor.

Before: SENTELLE, Chief Judge, TATEL and GRIFFITH,

Circuit Judges.

Opinion for the Court filed by Circuit Judge GRIFFITH.

2

GRIFFITH, Circuit Judge: The newly created Electric

Reliability Organization proposed that its costs be allocated

according to a method of computation called net energy for

load. Alcoa asks us to review the decision of the Federal

Energy Regulatory Commission that approved the proposal.

We find the decision reasonable and thus deny the petition for

review.

I.

Until recently, the reliability of the nation’s bulk-power

system depended on participants’ voluntary compliance with

industry standards. In 2005, Congress decided this

arrangement was no longer acceptable and enacted legislation

requiring the development of mandatory, FERC-approved

electric reliability standards. See Energy Policy Act of 2005,

Pub. L. No. 109-58, § 1211(b), 119 Stat. 594, 942; Mandatory

Reliability Standards for the Bulk-Power System, 72 Fed.

Reg. 16,416, 16,419 (Apr. 4, 2007). To carry out this change,

Congress added section 215 to the Federal Power Act (FPA),

which provides for the creation of a national Electric

Reliability Organization charged with establishing and

enforcing such standards. 16 U.S.C. § 824o(a)(2) (2006). Any

entity may apply, but FERC can certify only one Electric

Reliability Organization. Before doing so, the Commission

must determine that the applicant meets certain criteria.