Court of Appeals for the D.C. Circuit February 26, 2010, 08-1195 (Iberdrola Renewables, Inc. v. Federal Energy Regulatory Commission)

Also known as

United States · · · 26-02-2010

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued September 16, 2009 Decided February 26, 2010

No. 08-1195

IBERDROLA RENEWABLES, INCORPORATED,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

ALLIANCE PIPELINE L.P. AND INTERSTATE NATURAL GAS

ASSOCIATION OF AMERICA,

INTERVENORS

On Petition for Review of an Order

of the Federal Energy Regulatory Commission

Mark K. Lewis argued the cause and filed the briefs for

petitioner.

Judith A. Albert, Senior Attorney, Federal Energy

Regulatory Commission, argued the cause for respondent.

With her on the brief were Cynthia A. Marlette, General

Counsel, and Robert H. Solomon, Solicitor.

2

Virginia A. Seitz argued the cause for intervenors. With

her on the brief were Joan Dreskin, Dan Regan, Timm

Abendroth, and William A. Williams.

Before: SENTELLE, Chief Judge, GRIFFITH, Circuit Judge,

and SILBERMAN, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge GRIFFITH.

GRIFFITH, Circuit Judge: Although set against the

complicated regulatory framework of federal energy law, at

the end of the day, this petition for review of Federal Energy

Regulatory Commission (FERC) orders requires only our

straightforward application of the plain terms of a written

contract. The question is whether FERC arbitrarily or

capriciously read a contract to allow a pipeline to change its

rates without first obtaining FERC’s approval. Because the

contract expressly excludes such a role for FERC, we deny

the petition.

I.

Intervenor Alliance Pipeline L.P. operates an 887-mile

pipeline that transports natural gas from the North Dakota-

Canada border to the Chicago area. Alliance Pipeline L.P.,

Preliminary Determination on Non-Environmental Issues, 80

FERC ¶ 61,149, at 61,590 (1997) [hereinafter Preliminary

Determination]. Before Alliance began service on the

pipeline, each shipper chose to negotiate the rate it would pay

and committed that agreement to a written contract.

Read the full text