Court of Appeals for the D.C. Circuit February 26, 2010, 08-1195 (Iberdrola Renewables, Inc. v. Federal Energy Regulatory Commission)
Also known as
United States · · · 26-02-2010
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued September 16, 2009 Decided February 26, 2010
No. 08-1195
IBERDROLA RENEWABLES, INCORPORATED,
PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION,
RESPONDENT
ALLIANCE PIPELINE L.P. AND INTERSTATE NATURAL GAS
ASSOCIATION OF AMERICA,
INTERVENORS
On Petition for Review of an Order
of the Federal Energy Regulatory Commission
Mark K. Lewis argued the cause and filed the briefs for
petitioner.
Judith A. Albert, Senior Attorney, Federal Energy
Regulatory Commission, argued the cause for respondent.
With her on the brief were Cynthia A. Marlette, General
Counsel, and Robert H. Solomon, Solicitor.
2
Virginia A. Seitz argued the cause for intervenors. With
her on the brief were Joan Dreskin, Dan Regan, Timm
Abendroth, and William A. Williams.
Before: SENTELLE, Chief Judge, GRIFFITH, Circuit Judge,
and SILBERMAN, Senior Circuit Judge.
Opinion for the Court filed by Circuit Judge GRIFFITH.
GRIFFITH, Circuit Judge: Although set against the
complicated regulatory framework of federal energy law, at
the end of the day, this petition for review of Federal Energy
Regulatory Commission (FERC) orders requires only our
straightforward application of the plain terms of a written
contract. The question is whether FERC arbitrarily or
capriciously read a contract to allow a pipeline to change its
rates without first obtaining FERC’s approval. Because the
contract expressly excludes such a role for FERC, we deny
the petition.
I.
Intervenor Alliance Pipeline L.P. operates an 887-mile
pipeline that transports natural gas from the North Dakota-
Canada border to the Chicago area. Alliance Pipeline L.P.,
Preliminary Determination on Non-Environmental Issues, 80
FERC ¶ 61,149, at 61,590 (1997) [hereinafter Preliminary
Determination]. Before Alliance began service on the
pipeline, each shipper chose to negotiate the rate it would pay
and committed that agreement to a written contract.