District Court, District of Columbia March 8, 2011, Civil Action No. 2009-1232 (American Property Construction Company v. Sprenger Lang Foundation)

Also known as

United States · · · 08-03-2011

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF COLUMBIA

AMERICAN PROPERTY

CONSTRUCTION COMPANY,

Plaintiff/Counter-Defendant,

Civil Action No. 09-01232 (CKK)

v.

SPRENGER LANG FOUNDATION, et al.,

Defendants/Counter-Plaintiffs.

MEMORANDUM OPINION

(March 8, 2011)

This action involves a relatively straightforward contract dispute about construction

services. Plaintiff/Counter-Defendant American Property Construction Company (“APCC”)

commenced suit against Defendants/Counter-Plaintiffs Paul Sprenger (“Sprenger”), Jane Lang

(“Lang”), and the Sprenger Lang Foundation (collectively, “Defendants”), asserting claims for

breach of express and implied contract based upon Defendants’ alleged failure to remit payment

for construction services provided by APCC. Through this action, APCC seeks to recover

monetary damages in the amount of $339,727.50, exclusive of interest, as recompense for

services provided. Presently before the Court is Sprenger and Lang’s [37] Motion for Partial

Summary Judgment,1 which is directed towards challenging a discrete component of APCC’s

breach of contract claims—namely, a so-called “contingency” line item in the amount of

$85,830. Contending that there was no “meeting of the minds” as to the “contingency” line item,

Sprenger and Lang assert that summary judgment should be entered in their favor on this limited

1

The Sprenger Lang Foundation does not join in the motion.

issue. Based upon the parties’ submissions, the attachments thereto, the relevant authorities, and

the record as a whole, the Court concludes that there remains a genuine dispute as to the meaning

that the parties’ attached to the “contingency” line item and, accordingly, Sprenger and Lang’s

[37] Motion for Partial Summary Judgment shall be DENIED.2

I. BACKGROUND

APCC commenced this action against Defendants on July 2, 2009, asserting claims for

breach of express and implied contract. See Compl., Docket No. [1].