Ohio Court of Claims January 21, 2011, 2010-10939-AD (Zwick v. Ohio Dept. of Transp.)

Also known as

United States · · · 21-01-2011

[Cite as Zwick v. Ohio Dept. of Transp., 2011-Ohio-1766.]

Court of Claims of Ohio

The Ohio Judicial Center

65 South Front Street, Third Floor

Columbus, OH 43215

614.387.9800 or 1.800.824.8263

www.cco.state.oh.us

MICHAEL JAMES ZWICK

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant

Case No. 2010-10939-AD

Deputy Clerk Daniel R. Borchert

ENTRY OF DISMISSAL

{¶ 1} On September 29, 2010, plaintiff, Michael Zwick, filed a complaint against

defendant, Department of Transportation. Plaintiff asserts on September 16, 2010 at

approximately 12:30 p.m., while traveling northbound on State Route 128 underneath

the I-275/I-74 overpass his vehicle struck a series of metal plates causing damage.

Plaintiff seeks reimbursement for tire damage in the amount of $141.83. The filing fee

was paid.

{¶ 2} On November 22, 2010, defendant filed a motion to dismiss. In support of

the motion to dismiss, defendant stated in pertinent part:

{¶ 3} “Duke Energy was working in this area by permit to relocate two aerial

lines into two buried flex ducts along SR 128 under I-74. They were working on a utility

relocation project and ODOT’s permit was issued on September 2, 2010. The permit

has language that states ‘The permittee shall save harmless the State of Ohio and all of

its representatives from all suits, actions, or claims of any character brought on account

Case No. 2010-10939-AD -2- ENTRY

of any injuries or damages sustained by any person or property in consequence of any

neglect or on account of any act or omission as a result of the issuance of this permit’

(See Exhibit A). This permit mentions that Duke Energy was doing work associated

with ODOT Project HAM-74-7.76 but this project will not be sold until November 18,

2010 and the utility company is doing the relocation work in advance of the construction

project.”

{¶ 4} Plaintiff has not responded to defendant’s motion to dismiss.

{¶ 5} Defendant was not responsible for the work being performed at the site of

plaintiff’s incident.