Texas Court of Appeals, 4th District (San Antonio) March 2, 2011, 04-10-00631-CV (Lyda Swinerton Builders, Inc. v. Pools by Blue Haven, Inc.)

Also known as

United States · · · 02-03-2011

MEMORANDUM OPINION

No. 04-10-00631-CV

LYDA SWINERTON BUILDERS, INC.,

Appellant

v.

POOLS BY BLUE HAVEN, INC.,

Appellee

From the 288th Judicial District Court, Bexar County, Texas

Trial Court No. 2009-CI-20145

Honorable Solomon Casseb, III, Judge Presiding

Opinion by: Karen Angelini, Justice

Sitting: Karen Angelini, Justice

Phylis J. Speedlin, Justice

Steven C. Hilbig, Justice

Delivered and Filed: March 2, 2011

REVERSED AND REMANDED

The present appeal arises from the trial court’s denial of a motion to compel arbitration

filed by Lyda Swinerton Builders, Inc. (“Lyda”). We reverse the trial court’s orders denying

Lyda’s motion to compel arbitration and remand the case to the trial court for further

proceedings.

04-10-00631-CV

BACKGROUND

The facts pertinent to Lyda’s appeal are largely undisputed. On July 14, 2006, Lyda

entered into a construction contract with Riverwalk CY Hotel Partners, Ltd. (“Riverwalk”) to

construct a hotel known as the Marriott Courtyard at the San Antonio Riverwalk (the “Hotel”).

The construction agreement between Lyda and Riverwalk contained provisions for the mediation

of disputes. The agreement further provided that if formal mediation could not resolve a dispute,

binding arbitration under the Construction Industry Rules of the American Arbitration

Association was required.

Lyda subsequently entered into a subcontract (the “Subcontract”) with Pools by Blue

Haven, Inc. (“Blue Haven”) on March 8, 2007, concerning the design/construction of a

swimming pool and spa at the Hotel. The Subcontract contained various dispute resolution

clauses, including:

15.

Read the full text