United States Court of Federal Claims August 19, 2011, No. 05-1054C (K-Con Building Systems, Inc. v. United States)

Also known as

United States · · · 19-08-2011

OPINION AND ORDER

SWEENEY, Judge.

Plaintiff K-Con Building Systems, Inc. filed three suits in this court concerning its contracts with the United States Coast Guard (“Coast Guard”) for the design and construction of prefabricated metal buildings in Elizabeth City, North Carolina, St. Peters-burg, Florida, and Port Huron, Michigan. The three suits share many similarities, but there are meaningful differences that require the court to address each suit separately. The court previously ruled on plaintiffs motion for partial summary judgment in the Elizabeth City suit. In this case, which concerns the building in Port Huron, plaintiff moves for summary judgment on three issues: whether the liquidated damages rate specified in the contract constitutes an unenforceable penalty; whether remission of some liquidated damages is appropriate; and whether it is entitled to a change order. For the reasons set forth below, the court denies plaintiffs motion.

I. BACKGROUND

In April 2001, the United States General Services Administration (“GSA”) awarded plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking Shelters.1 Pl.’s App. 1-9. Subsequently, in the fall of 2003, the Coast Guard solicited proposals for the design and construction of a prefabricated structure to serve as a cutter support team building in Port Huron. Id. at 11-13,82.

A. Contract Requirements

As set forth in the Scope of Services section of the request for proposals (“RFP”), the Coast Guard contemplated that the successful contractor would design the building based on the contract requirements, submit the design to the Coast Guard in three phases (a “50% design,” a “90% design,” and a “100% design”), and, upon the Coast Guard’s approval of the 50% design, begin construction. Id. at 85. The 50% design was due twenty-one days after contract award, and the Coast Guard had five days within which to provide the contractor with its comments. Id.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.