Appellate Division of the Supreme Court of the State of New York April 17, 2012 (Environmental Technology Group, Inc. v. Gannett Fleming Project Development Corp.)

Also known as

United States · · · 17-04-2012

In an action to recover damages for breach of contract and unjust enrichment, the plaintiff appeals, as limited by its brief, *944from so much of an order of the Supreme Court, Suffolk County (Pines, J.), dated February 1, 2011, as granted that branch of the defendant’s motion which was for summary judgment dismissing the cause of action to recover damages for breach of contract.

Ordered that the order is reversed insofar as appealed from, on the law, with costs, and that branch of the defendant’s motion which was for summary judgment dismissing the cause of action to recover damages for breach of contract is denied.

On April 25, 2005, the plaintiff entered into a master services agreement with the defendant to provide environmental cleanup services at a former waste disposal site. Under the terms of the agreement, the defendant was not responsible for the payment of invoices it received from the plaintiff more than 90 days after the plaintiff performed the invoiced work. The agreement also gave the defendant “the unrestricted right” to terminate the plaintiffs services. On January 9, 2007, after certain disputes over billing and cost overruns arose, the plaintiff executed a release in which it agreed to accept the sum of $301,000 as “full payment of [its] services through June 1, 2006.” About three weeks later, on January 31, 2007, the defendant terminated the plaintiffs services and instructed the plaintiff to stop all work on the project.

The plaintiff subsequently commenced this action seeking, inter alia, to recover the sum of $514,212.41 for unpaid work billed on 16 invoices. The defendant moved for summary judgment dismissing the complaint, arguing that the plaintiff was not entitled to payment because some of the invoices were submitted more than 90 days after the work was performed, and other invoices sought payment for work encompassed by the release, or performed after the plaintiff was specifically instructed to stop work.

Read the full text

This document is published by courtlistener.com.

Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.