Court of Appeals for the D.C. Circuit December 13, 2013, 19-5139 (TC Ravenswood, LLC v. Federal Energy Regulatory Commission)
Also known as
United States · · · 13-12-2013
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued October 15, 2013 Decided December 13, 2013
No. 12-1008
TC RAVENSWOOD, LLC,
PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION,
RESPONDENT
ASTORIA GENERATING COMPANY, L.P., ET AL.,
INTERVENORS
Consolidated with 12-1081
On Petitions for Review of Orders of the
Federal Energy Regulatory Commission
Kenneth L. Wiseman argued the cause for petitioner TC
Ravenswood, LLC. Robert C. Fallon argued the cause for
petitioner The NRG Companies. With them on the briefs were
Mark F. Sundback, Lisa M. Purdy, William M. Rappolt, J.
Peter Ripley, Kristine L. Delkus, Christopher C. O’Hara,
Blake R. Urban, James M. D’Andrea, Marcia A. Stanford, and
Abraham H. Silverman.
2
Jennifer S. Amerkhail, Attorney, Federal Energy
Regulatory Commission, argued the cause for respondent.
With her on the brief were David L. Morenoff, Acting General
Counsel, and Robert H. Solomon, Solicitor.
Robert M. Loughney argued the cause for intervenors City
of New York and the New York State Public Service
Commission. On the brief were Kevin M. Lang, Sean Mullany,
and Peter McGowan.
Kevin M. Lang and Neil H. Butterklee were on the brief for
intervenors Consolidated Edison Company of New York, Inc.,
et al. in support of respondent.
Shawn Patrick Regan and Ted J. Murphy were on the brief
for intervenor New York Independent System Operator, Inc. in
support of respondent.
Before: TATEL and KAVANAUGH, Circuit Judges, and
SENTELLE, Senior Circuit Judge.
Opinion for the Court filed by Circuit Judge TATEL.
TATEL, Circuit Judge: Utilizing administratively
determined “demand curves,” the New York Independent
System Operator (NYISO) holds monthly auctions to set the
price of electrical power capacity in New York. Petitioners,
owners and operators of electrical power generation facilities,
challenge several Federal Energy Regulatory Commission
orders concerning the creation of the 2011–2014 demand
curves.