Court of Appeals for the Fifth Circuit January 22, 2013, 11-60492 (Ergon-West Virginia, Inc. v. Dynegy Marketing & Trade)
Also known as
United States · · · 22-01-2013
combined-opinion
Case: 11-60492 Document: 00512119951 Page: 1 Date Filed: 01/22/2013
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT United States Court of Appeals
Fifth Circuit
FILED
January 22, 2013
No. 11-60492 Lyle W. Cayce
Clerk
ERGON-WEST VIRGINIA, INCORPORATED,
Plaintiff - Appellee
ERGON REFINING, INCORPORATED,
Plaintiff - Cross Appellant
v.
DYNEGY MARKETING & TRADE,
Defendant - Appellant Cross Appellee
ERGON REFINING, INCORPORATED,
Plaintiff - Cross Appellant
v.
DYNEGY MARKETING & TRADE,
Defendant - Appellant Cross Appellee
Appeals from the United States District Court
for the Southern District of Mississippi
Case: 11-60492 Document: 00512119951 Page: 2 Date Filed: 01/22/2013
No. 11-60492
Before REAVLEY, DENNIS, and CLEMENT, Circuit Judges.
EDITH BROWN CLEMENT, Circuit Judge:
Appellant-Cross Appellee Dynegy Marketing and Trade (“Dynegy”) and
Cross Appellant Ergon Refining appeal the district court’s holding that Dynegy
had no contractual duty to Ergon Refining to attempt to secure replacement gas
after declaring force majeure in response to hurricane damage, but did have such
a duty to Ergon-West Virginia (“Ergon-WV”) under a separate contract. For the
reasons provided below, we hold that neither contract required Dynegy to
attempt to secure replacement gas during the force majeure period. We
AFFIRM the district court’s ruling on the Ergon Refining contract and
REVERSE and RENDER with respect to the Ergon-WV contract.
FACTUAL AND PROCEDURAL BACKGROUND
This is a contract dispute between a natural gas clearinghouse, Dynegy,
and two separate entities that manage refinery plants, Ergon Refining and
Ergon-WV. The two Ergon entities1 have contracted with Dynegy to provide
their natural gas supply since 19932 and 1997, respectively. When Hurricanes
Katrina and Rita hit in 2005 and caused extensive damage to the gas industry’s
infrastructure, Dynegy’s own internally designated suppliers declared force
majeure.