District Court, D. Oregon August 8, 2013, No. 12-cv-00133-HU (United States ex rel. TBH & Associates, LLC v. Wilson Construction Co.)

Also known as

United States · · · 08-08-2013

ORDER ON DEFENDANTS’ MOTION FOR PARTIAL SUMMARY JUDGMENT

HUBEL, United States Magistrate Judge:

This contract dispute relates to construction of the McNary-John Day Transmission Line (the “Project”) by the Bonneville Power Administration (“BPA”). The defendant Wilson Construction Co. was general contractor for the Project.