IN THE UNITED STATES BANKRUPTCY COURT
2 FOR THE DISTRICT OF PUERTO RICO
3 IN RE: CASE NO. 02-02887(ESL)
4 REDONDO CONSTRUCTION CHAPTER 11
CORPORATION
5
6 Debtor
REDONDO CONSTRUCTION ADV. PROC. NO. 03-00192 (ESL)
7 CORPORATION ADV. PROC. NO. 03-00194 (ESL)
ADV. PROC. NO. 03-00195 (ESL)
8 Plaintiff
9
vs.
10
PUERTO RICO HIGHWAY AND
11 TRANSPORTATION AUTHORITY
12
Defendant
13
OPINION AND ORDER
14
15 These adversary proceedings are before the court upon the Brief as to [] Extended Home
16 Office Overhead Damages filed by Plaintiff Redondo Construction Corp. (“Redondo”) (Adv.
17 Proc. No. 03-00192 Docket No. 333, Adv. Proc. No. 03-00194 Docket No. 293 and Adv. Proc.
18 No. 03-00195 Docket No. 265). Each adversary proceeding corresponds to a different project
19 where Redondo intervened as a contractor: Adv. Proc. No. 03-00192 corresponds to project
20 Desvío Sur de Patillas (“Desvío Sur de Patillas”), Adv. Proc. No. 03-00194 corresponds to PR 2
21 Mayaguez (“PR 2 Mayaguez”), and Adv. Proc. No. 03-00195 corresponds to Dorado-Toa Alta
22 (“Dorado-Toa Alta”). Also before the court is Puerto Rico Highway and Transportation
23 Authority’s (“PRHTA”) Brief on the home-office overhead damages, but only in regards to the
24 PR 2 Mayaguez Project (Adv. Proc. No. 03-00194 Docket No. 209). PRHTA did not file briefs
25 in Adv. Proc. Nos. 03-00192 and 03-00195. For the reasons stated below, Redondo’s claims for
26 home-office overhead damages are only allowed under the percentage-of-direct-costs approach.
27
1 Procedural Background
2 On January 13, 2014, this court entered an Opinion and Order (Lamoutte. B.J.) in the
3 instant adversary proceedings granting Redondo pre-judgment interest at six percent (6%) under
4 Article 1061 of the Civil Code of Puerto Rico, 31 L.P.R.A. § 3025, with an accrual period
5 starting from the stipulated dates of substantial completion until PRHTA’s final payment on the
6 principal of the principal amounts for each project.